10 Time & Work Math Problems for BCS & Bank Jobs BD
1. Hasan and Kamal together can complete a project in 12 days. If Hasan works at half of his normal efficiency and Kamal works at 3 times his normal efficiency, the task is completed in 9 days. How many days would Hasan take to complete the task alone?
Solution:
Let Hasan's 1-day work be $h$ and Kamal's 1-day work be $k$.
From the first condition: $h + k = \frac{1}{12}$
From the second condition: $\frac{h}{2} + 3k = \frac{1}{9}$
Multiply the first equation by 3 to match the $k$ terms: $3h + 3k = \frac{3}{12} = \frac{1}{4}$
Now, subtract the second equation from this new equation:
$(3h + 3k) - (\frac{h}{2} + 3k) = \frac{1}{4} - \frac{1}{9}$
$\frac{5h}{2} = \frac{5}{36}$
$h = \frac{5}{36} \times \frac{2}{5} = \frac{1}{18}$
Since Hasan's 1-day work is $\frac{1}{18}$, he takes 18 days to complete the work alone.
So, the answer is B
2. A mason can build a specific brick wall in 30 days. However, a laborer, upset with the pay, secretly demolishes the wall at night. Working alone, the laborer could completely demolish the wall in 40 days. If they act on alternate days starting with the mason building on the first day, in how many days will the wall be completely built for the very first time?
Solution:
Net work done in a 2-day cycle = $\frac{1}{30} - \frac{1}{40} = \frac{4 - 3}{120} = \frac{1}{120}$.
A common trap is to assume it takes $120 \times 2 = 240$ days. However, on the final step, the mason will finish building the wall, and the laborer will not have a chance to demolish it.
The mason's work on his final day is $\frac{1}{30}$. We must calculate how long it takes to reach the point just before this final day.
Target work before the final day = $1 - \frac{1}{30} = \frac{29}{30}$.
Let $N$ be the number of 2-day cycles needed to reach this target: $N \times \frac{1}{120} = \frac{29}{30}$.
$N = \frac{29 \times 120}{30} = 29 \times 4 = 116$ cycles.
116 cycles $\times 2$ = 232 days. In 232 days, exactly $\frac{29}{30}$ of the wall is built.
On the 233rd day, the mason comes in and completes the remaining $\frac{1}{30}$ of the work. The wall is now fully built.
So, the answer is B
3. Arif works on a job for 4 days and leaves. Babu then steps in and finishes the remaining work in 18 days. Had Arif worked for 6 days instead, Babu would have finished the remaining work in 12 days. How long would it take for Arif and Babu to finish the entire job if they worked together from the start?
Solution:
Let Arif's 1-day work be $a$ and Babu's 1-day work be $b$.
Scenario 1: $4a + 18b = 1$ (Whole work complete)
Scenario 2: $6a + 12b = 1$
Equate the two expressions since both equal 1:
$4a + 18b = 6a + 12b \Rightarrow 2a = 6b \Rightarrow a = 3b$. (Arif is 3 times as efficient as Babu).
Substitute $a = 3b$ back into Scenario 1: $4(3b) + 18b = 1 \Rightarrow 12b + 18b = 1 \Rightarrow 30b = 1 \Rightarrow b = \frac{1}{30}$. Babu takes 30 days.
Since $a = 3b$, $a = 3(\frac{1}{30}) = \frac{1}{10}$. Arif takes 10 days.
Working together, their 1-day work is $a + b = \frac{1}{10} + \frac{1}{30} = \frac{3+1}{30} = \frac{4}{30} = \frac{2}{15}$.
Total time taken together = $\frac{15}{2} = 7.5$ days.
So, the answer is B
4. Two inlet pipes can fill a WASA water tank in 20 minutes and 24 minutes, respectively. A third waste pipe at the bottom can empty out 3 gallons per minute. If all three pipes are opened simultaneously, the tank takes exactly 15 minutes to fill. What is the total capacity of the tank?
Solution:
Let the waste pipe take $x$ minutes to empty the full tank alone. Its 1-minute work is $-\frac{1}{x}$.
Work of Pipe A in 1 min = $\frac{1}{20}$. Work of Pipe B in 1 min = $\frac{1}{24}$.
Net work of all three pipes in 1 min = $\frac{1}{15}$.
Equation: $\frac{1}{20} + \frac{1}{24} - \frac{1}{x} = \frac{1}{15}$
$\frac{6 + 5}{120} - \frac{1}{x} = \frac{8}{120}$ (converting all fractions to a common denominator of 120)
$\frac{11}{120} - \frac{8}{120} = \frac{1}{x}$
$\frac{3}{120} = \frac{1}{x} \Rightarrow \frac{1}{40} = \frac{1}{x} \Rightarrow x = 40$.
The waste pipe takes 40 minutes to empty the tank. Since it empties at a rate of 3 gallons per minute, the Capacity = $40 \text{ mins} \times 3 \text{ gallons/min} = 120$ gallons.
So, the answer is C
5. A team of 2 men and 3 boys can finish a landscaping job in 10 days. A different team of 3 men and 2 boys can finish the exact same job in 8 days. In how many days can a team of 2 men and 1 boy finish the work?
Solution:
We use the concept of equating total man-days of work.
$(2M + 3B) \times 10 = (3M + 2B) \times 8$
$20M + 30B = 24M + 16B$
$14B = 4M \Rightarrow 2M = 7B$. (The work of 2 Men is equivalent to 7 Boys).
Substitute this into the first team's equation to find the work in terms of purely boys:
$(2M + 3B) \rightarrow (7B + 3B) = 10B$. So, 10 Boys can do the work in 10 days. Total work = $10 \times 10 = 100$ Boy-days.
Now, find the equivalent of the target team (2 Men and 1 Boy):
$2M + 1B = 7B + 1B = 8B$.
Time taken by 8 Boys = $\frac{\text{Total Work}}{\text{Workers}} = \frac{100}{8} = 12.5$ days.
So, the answer is B
6. A government contractor employed 30 men to complete a bridge repair in 100 days. After 25 days, an inspection revealed that only 20% of the required work had been completed. How many additional men must the contractor hire to ensure the work is completed exactly on the original schedule?
Solution:
Use the formula: $\frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2}$
Initial condition: $M_1 = 30$ men, $D_1 = 25$ days, $W_1 = 20\%$ (or $0.2$).
Target condition: The remaining time is $100 - 25 = 75$ days ($D_2$). The remaining work is $100\% - 20\% = 80\%$ (or $0.8$) ($W_2$). We need to find $M_2$ (total men needed).
$\frac{30 \times 25}{0.2} = \frac{M_2 \times 75}{0.8}$
$3750 = \frac{M_2 \times 75}{4}$ (Simplifying the denominators by multiplying both sides by 0.8)
$M_2 = \frac{3750 \times 4}{75} = 50 \times 4 = 200$? Let's re-calculate.
$\frac{750}{0.2} = \frac{75M_2}{0.8} \Rightarrow 3750 = 93.75 \times M_2 \Rightarrow M_2 = \frac{3750}{93.75} = 40$ men.
Total men required to finish on time is 40. Since 30 men are already working, the extra men required = $40 - 30 = 10$.
So, the answer is A
7. X and Y take up a software development contract for Tk 4,500. X alone can do the work in 10 days, and Y alone can do it in 15 days. They work together for 5 days, after which they leave due to an emergency. Z is hired to finish the remaining work, which he completes in 2 days. How much of the total contract money should Z receive based on the work he performed?
Solution:
Wages are strictly distributed in proportion to the fraction of total work completed by each person.
X's 1-day work is $\frac{1}{10}$. In 5 days, X completes $5 \times \frac{1}{10} = \frac{1}{2}$ of the work.
Y's 1-day work is $\frac{1}{15}$. In 5 days, Y completes $5 \times \frac{1}{15} = \frac{1}{3}$ of the work.
Total work done by X and Y together = $\frac{1}{2} + \frac{1}{3} = \frac{3+2}{6} = \frac{5}{6}$.
The remaining work that Z had to complete is $1 - \frac{5}{6} = \frac{1}{6}$.
Therefore, Z's share is $\frac{1}{6}$ of the total contract amount.
Z's Share = $\frac{1}{6} \times 4500 = 750$.
So, the answer is B
8. A and B can do a piece of work in 45 days and 40 days respectively. They began the work together, but A left after some days, leaving B to finish the remaining work alone. If B took exactly 23 days to finish the remaining work, after how many days from the start did A leave?
Solution:
First, calculate the work B did alone in his final 23 days.
B's 1-day work is $\frac{1}{40}$. Work done by B in 23 days = $23 \times \frac{1}{40} = \frac{23}{40}$.
This means the work done by A and B together before A left was $1 - \frac{23}{40} = \frac{17}{40}$.
Now, find their combined 1-day work: $\frac{1}{45} + \frac{1}{40} = \frac{8+9}{360} = \frac{17}{360}$.
Let $d$ be the number of days they worked together.
$d \times (\frac{17}{360}) = \frac{17}{40}$
$d = \frac{17}{40} \times \frac{360}{17} = \frac{360}{40} = 9$ days.
So, the answer is C
9. A cistern has a crack at the bottom which would empty a full tank in 8 hours. A supply tap is turned on which admits 6 liters of water per minute into the cistern. Despite the tap running, the tank is emptied in exactly 12 hours. What is the total volumetric capacity of the cistern?
Solution:
Let the supply tap take $x$ hours to fill the tank alone. Its rate is $+\frac{1}{x}$.
The leak empties the tank in 8 hours. Its rate is $-\frac{1}{8}$.
Together, the net result is emptying the tank in 12 hours. So the net rate is $-\frac{1}{12}$.
$\frac{1}{x} - \frac{1}{8} = -\frac{1}{12}$
$\frac{1}{x} = \frac{1}{8} - \frac{1}{12} = \frac{3 - 2}{24} = \frac{1}{24}$.
This means the supply tap alone could fill the tank in 24 hours.
Convert the time into minutes because the flow rate is in liters per minute: $24 \text{ hours} \times 60 \text{ mins} = 1440 \text{ minutes}$.
Capacity = $1440 \text{ mins} \times 6 \text{ liters/min} = 8640$ liters.
So, the answer is B
10. Three employees P, Q, and R can complete a filing task in 10, 15, and 30 days respectively. P works on the task every single day. Q and R only join P to help every third day (i.e., on Day 3, Day 6, Day 9, etc.). In how many days will the entire task be completed?
Solution:
Let's calculate the work done in one 3-day cycle.
Day 1: P works alone $\Rightarrow \frac{1}{10}$ of work.
Day 2: P works alone $\Rightarrow \frac{1}{10}$ of work.
Day 3: P, Q, and R work together $\Rightarrow \frac{1}{10} + \frac{1}{15} + \frac{1}{30} = \frac{3+2+1}{30} = \frac{6}{30} = \frac{1}{5}$ of work.
Total work done in one 3-day cycle = $\frac{1}{10} + \frac{1}{10} + \frac{1}{5} = \frac{2}{10} + \frac{2}{10} = \frac{4}{10} = \frac{2}{5}$.
In 2 cycles (6 days), the work done is $2 \times \frac{2}{5} = \frac{4}{5}$.
The remaining work is $1 - \frac{4}{5} = \frac{1}{5}$.
Now the 3rd cycle begins.
On Day 7, P works alone and does $\frac{1}{10}$. Remaining work = $\frac{1}{5} - \frac{1}{10} = \frac{1}{10}$.
On Day 8, P works alone again and does exactly the remaining $\frac{1}{10}$ of the work.
The task is completely finished exactly at the end of the 8th day.
So, the answer is C
💬Community Discussion
0 Comments
Sign in to join the discussion
Sign In